2022 July Construction Update

Written by All West Communications | Jun 29, 2022 8:43:00 PM

Construction season is in full swing, and crews are working hard to complete streets! We were off to a slow start due to spring storms that made the ground too muddy to build, but now the ground is firming up, and crews can continue projects. There are four phases in construction before we can connect your home to speeds up to 1 Gig.

  1. Design phase

During the design phase, our engineers are planning where our infrastructure will be, getting permits approved, and making sure everything is laid out in detail for construction to get started.

  1. Lay conduit

The conduit is the tube that houses our fiber lines, so they don’t get damaged while in the ground. We use a Ditch Witch machine to bury the conduit, which gives us the framework for our network.

3.  Install Fiber


Fiber is the cable that brings the internet to your home at the speed of light. Once the conduit is in place, we pull our fiber through it. There are multiple fiber strands per cable, which gives our customers their own dedicated line.

  1. Splicing and testing

After everything is in place, we do what is called splicing or separating each dedicated line of fiber and connecting it to a cabinet that feeds into your home. And after everything is in place, we test it to ensure our customers get the fastest speeds around without a hitch.

Kemmerer

In Kemmerer, we have several streets undergoing splicing and testing, and customers will soon be called to schedule their installation. If you live on Fifth West Ct. or Uinta Dr., your streets are just about ready to go.

Huntsville, Eden & Liberty

In Huntsville, Eden, and Liberty, construction crews are laying conduit and getting ready to install Fiber. These areas are on schedule to get connected in late August.

Keep an eye on our construction timeline for updates. While you’re waiting for us to complete your area, sign up early, and receive free installation ($200+ value).