The weather is getting colder, and the leaves are changing – it’s finally Fall! Our crews are working hard to connect as many customers as possible to our expanding network and build even more fiber between now and the end of the year*.
Here is a breakdown of the progress we’re making:
Red Lines – Partial ducts are in the ground
Blue Lines – Duct is in the ground, but no fiber yet
Magenta Lines – Fiber has been placed
Eden and Liberty, UT
Installs are projected to begin in mid-November for our builds in Eden and Huntsville.
Huntsville, UT
Kemmerer, WY
In order to connect as many customers as possible before our construction season ends, we will have contractors coming in at the end of the month to start installs in Kemmerer.
*As we start to enter the winter season, our construction team will continue building until the ground freezes. Once the ground freezes, all builds will be put on hold until the spring.